© Railway Wonders of the World 2012-22  Contents  |  Site Map  |  Contact

Sydney Harbour Bridge


One of the World’s Greatest Railway Links


MARVELS OF ENGINEERING - 3


Sydney Harbour bridge








CROSSING SYDNEY HARBOUR in a single span of 1,650 ft between the centres of the hinges, at a clear height of 170 ft above the water, this bridge carries rails, road, and footways, the total width being 160 ft. The arch span, which rises to a height of 440 ft, is flanked by massive masonry pylons, with five steel approach spans on either side of the harbour. The contract was let in March, 1924, the two halves of the main span met in August, 1930, and the bridge opened to traffic in March, 1932.



THE bridge spanning Sydney Harbour - an anchorage that could accommodate the whole British navy at one time - is one of the most spectacular steel structures in the world. The gigantic arch has a span of 1,650 ft and the approach spans, five on either side of the harbour, bring the total length of the bridge to 3,770 ft. Flanking the arch are four granite pylons towering 285 ft above the water. With a headroom of 170 ft beneath the roadway, the largest liners can proceed up the harbour from the Pacific Ocean.


As early as 1815 a suggestion for the bridging of Sydney Harbour was submitted to the Government, and the subject was raised at intervals throughout the remainder of the last century. By 1900 development in and around Sydney had made enormous progress, and in that year the New South Wales Government invited competitive designs for a bridge. Numerous proposals were made but no contract was placed. During 1911-12, however, the Public Works Committee held a lengthy inquiry, finally recommending the building of a cantilever bridge from Dawes Point to Milsons Point, linking the City of Sydney with the rapidly developing residential area north of the harbour.


As a railway link, of course, the bridge was of paramount importance, not only to join the northern suburbs with the City, but also to unite the lines north of Sydney with those serving the eastern, western and southern suburbs. With the Pacific Ocean to the east and very important docks to the west of its position, it was likewise imperative that the bridge should provide unimpeded passage for the largest ships.


In January, 1923, tenders were invited for the building of a bridge, the layout and span of which were defined by the Government’s engineer, Dr. J. C, C. Bradfield, There was keen competition to secure the contract. It was eventually awarded by the New South Wales Government in March, 1924, to a British firm, Dorman Long & Co, Ltd, of Middlesbrough. A note of regret echoes in the story of the contract. The decision to tender for the construction was due to the late Sir Arthur Dorman and the late Sir Hugh Bell, and the successful completion of the bridge was in no small measure due to their initiative and advice. They lived to see the arch finished but were not spared to see the completion of the bridge.


Mr. Ralph Freeman, consulting engineer to Dorman Long & Co, prepared designs for three different types of bridge; the arch actually built, a cantilever arch and a cantilever bridge. Alternative combinations of these types, with and without pylons, necessitated the preparation of seven different projects. The design chosen by the Government was the Company’s tender for an arch bridge with granite piers and granite pylons, to cost £4,217,721. The architectural features of the masonry conformed to the designs of Sir John Burnet and Partners.


ANCHORAGE ROPES being dismantled at the South Pylon after the closing of the main arch





















ANCHORAGE ROPES being dismantled at the South Pylon after the closing of the main arch. The arch was erected by building out the two half-arches as cantilevers from each shore. Each half-arch was anchored in position by 128 steel wire ropes of 2¾-in diameter and about 1,200 ft long. Two haulage winches were employed for withdrawing the ropes that were finally wound into coils for shipment back to England.



The whole of the steel used - with the exception of a small part purchased from Australian rolling mills, the main bearings, and some special forgings - was produced by Dorman Long and Co, Ltd, at Middlesbrough from their own raw materials. The construction of the steel work, some of it of a size and weight without precedent, its erection and all the civil engineering work in connexion with the completion of the bridge, were undertaken by the firm’s own staff and employees under the personal supervision of Mr. Lawrence Ennis, OBE, a director of the Company, who was in sole charge of the work in Sydney during the construction period. The skilled and unskilled labour was obtained in Australia.


The weight of steel involved in the contract was 51,000 tons, of which 38,000 tons are in the arch. Most of this great mass of metal was shipped to the bridge site from Middlesbrough - a journey of nearly twelve thousand miles. The great size of the structure was by no means the only difficulty with which the engineers had to contend.


Weight alone called for the most exacting accuracy in calculating the proportions of the various girders and components, and the provision of massive foundations deep in the solid rock of the harbour shore. The effect of the wind on so large an area had to be countered by a system of cross-bracing and other forms of strengthening. The effects of rust and corrosion were guarded against by elaborate systems of cover-plates, man-holes, and the provision of stairways, footways and fencing, so that all parts of the bridge are accessible for inspection and painting.


Heat and cold were factors that required the most careful consideration. These factors - always important - were especially so at Sydney, where the effect on the unusual length - 3,770 ft - of the normal expansion and contraction of heat and cold was remarkable. The trackways of Sydney Harbour bridge are nearly a foot longer in day-time than at night-time, and special expansion joints are arranged to permit of this elongation. It is in the mighty arch, however, that the greatest expansion takes place. A vital feature of the design, therefore, is the method of supporting the arch. It rests on four enormous hinges, and is free to rise in the centre - like a colossal yet superbly tempered sword bending in the hands of some mythological giant. By a compensation of nature, the trackway remains comparatively level, as the supporting “hangers” from which it is supported also lengthen under the effect of heat, and thus neutralize the upward lift of the arch. This trackway, or deck, is 160 ft wide, and comprises a central roadway, 57 ft wide, flanked by four railway tracks (two of 4 ft 8½-in gauge on either side), and two 10 ft footways.


The loads specified in the contract for these trackways give some idea of the service demanded of the bridge. The footways have had to be capable of supporting a load of 100 lb per square foot of their surface. The roadway had to carry a motor lorry (12 ft by 6 ft wheelbase) occupying a space of 30 ft by 12 ft in any position. The front axle load was not to exceed 18,000 lb, and that of the back axle, 36,000 lb. The remainder of the roadway load was to be 100 lb per sq ft. Requirements for the railway load were for the support on each track of two locomotives, each 65 ft long and weighing 360,000 lb, followed by a train weighing 2,200 lb per ft of its length.


DIAGRAM SHOWING METHOD OF ROPE ANCHORAGE during the erection of the Sydney Harbour bridge









THE TUNNELS for the rope anchorage at either end were driven into rock at an angle of about 45° to the horizontal. The lowest point was some 100 ft below the surface, and the peculiar shape rendered excavation difficult. Spoil was removed by skips running on narrow gauge inclines. The skips were hauled by an electric winch. To provide a seating for ropes throughout their bearing on the face of the rock tunnel it was necessary to form a suitable surface. This was achieved by setting up specially corrugated sheets bent to the true curve and backed with concrete. DIAGRAM SHOWING METHOD OF ROPE ANCHORAGE during the erection of the two half-arches. Steel wire ropes were passed from the top of one arch end-post through a tunnel - 25 ft by 7 ft - in rock, and back to the opposite end-post, so that the complete anchorage formed a U-shaped bend. To guide the ropes into the correct alinement concrete saddles were built at the tunnel’s mouths and on the pylons.



We have already outlined the principal dimensions of the bridge, but the following particulars give an indication of the arrangements and massive proportions of the component parts. The arch is composed of four main members, rising from the hinges to which we referred earlier, and the topmost pair comprise what is known as the “upper chord”. The under pair, much larger and heavier in section, form the “lower chord”. The chords are joined by vertical girders or “trusses” forming twenty-eight panels on either side of the arch. These panels are braced by diagonal girders giving each the appearance of the letter N. The chords on one side of the arch are connected at the extremities of the vertical trusses to those on the other side by cross ties and diagonals.


The hinges are 27 ft 6-in above mean water-level, and above them the lower chord of the arch rises 350 ft. The depth of the arch (length of vertical trusses) at the crown is 60 ft, and at the hinges it is approximately 188 ft. The measurement from truss centres on one side to those on the other is 98 ft 6-in, and the length of each N panel is approximately 59 ft.


The lower chord, resembling three very long rectangular steel boxes placed side by side, varies in depth from 4 ft at the centre of the arch to 8 ft 3-in at the bearings. The sides of these boxes are I shaped in section, and are built up of steel angles 12-in by 12-in, generally 1¼-in thick. The box sides or web plates are 2-in thick. The three boxes are divided longitudinally down the centre of the middle box to facilitate handling by the cranes; a final joint was made when the two portions were in position. In addition to this joint, the members were further subdivided horizontally, and as building proceeded were joined by means of splices.


Apart from the increased depth of the web plates which has been referred to, the section of the chord members was enlarged by adding side plates and by increasing the thickness of the flange plates forming the central portion of the I’s.


The upper chord has a constant depth of 3 ft 4-in, but variations in section are obtained by the addition of side plates and changes in the thicknesses of webs and flanges. The flange angles are also varied from 12-in by 12-in near the centre of the span to 8-in by 8-in near the hinges. The construction of the upper chord members is similar to that of the lower chord.


The four bearings that carry, through the hinges, the whole weight of the bridge, each withstands a pressure of 19,700 tons. The bearings are inclined at an angle of 45 degrees to the horizontal, and rest on immense concrete foundations laid on the solid rock. This part of the work will be described later.


The pressure from the lower chord of the arch is received on an upper saddle of forged steel resting on a pin 14½-in in diameter and 13 ft 8-in long. This pin rests on a lower saddle forging, supported by two plates forming an inverted V; each plate is 9½-in thick, 9 ft 6-in deep, 24 ft long at the base, and 13 ft 6-in long at the top. This method of construction distributes the pressure on the pin over the base.


THE CONTROL CABIN of one of the giant creeper cranes used on the Sydney Harbour bridge










THE CONTROL CABIN of one of the giant creeper cranes. The crane drivers were given orders by telephone from officials working some 400 ft below. When erecting the bridge each crane travelled forward on the top chords of the structure, and in each new position built up another part of the bridge in front of itself. The cranes were first tested in England.



The main web plates are connected together by ten transverse cast steel diaphragms. The lower edges of the web plates rest on six steel base castings interlocked and fitted together, machined below and on the bearing faces. The lower forged saddle, web plates, diaphragms and base castings are all interconnected with fitted 4-in diameter bolts. These bearings were manufactured complete by the Darlington Forge Co, Ltd, and as each is approximately the size of a bungalow, a reasonable degree of error might be expected in fitting the component parts.


The manufacturers and contractors had other views, however. The main components of the bearings were fitted to a limit of error of 1-1,000th of an inch. The bolts are fitted to a limit of error of 1-10,000th of an inch. Such is British bridge building.


The vertical trusses or end posts, rising from the bearings at either end of the bridge, are of immense size - over 190 ft in total height, and constructed in a similar manner to the upper and lower chord members. The posts, centre to centre, are 98 ft 6-in apart, and form a huge rectangle, braced with cross members and diagonals. These posts carry the ends of the bridge deck. The posts are pivoted on the bearings, and the upper ends are capable of movement to and from the pylons as the arch expands or contracts with changes in temperature. This movement, at deck level, may be as much as 8-in at either end of the bridge.


The deck, in addition to the support of cross girders at the end posts, is also carried on cross girders attached to the vertical trusses of the first three panels at either bridge-end. The rest of the deck is supported by “hangers” from the lower chord; these will be described later.


The construction of the deck and the ingenious method of carrying the railway tracks are especially interesting.


The deck comprises longitudinal members, known as “stringers”, connected by cross girders and strengthened by diagonal cross bracing. The heaviest loads upon the bridge are, of course, the trains running on the four railway tracks; for this reason these are laid on either side of the hangers on both sides of the structure. One railway track on either side of the bridge is thus outside the great arch; beyond these are the footways. They are surfaced with asphalt on a foundation of breeze concrete laid on steel troughs. The steel troughing is carried by close-latticed steel parapet-stringers resting on the deck cross girders.


Between the inner railway tracks is the 57 ft roadway, surfaced with asphalt on a foundation of coke concrete. This light-weight concrete is carried in pressed steel troughing that spans across transverse steel joists bent to the camber of the road. The road joists are supported on six plate girder stringers spaced 11 ft 5½-in apart.


An interesting addition to the deck structure is the system of latticed girder stringers of box form under the centre lines of the arch trusses between the inner railway tracks. These stringers, the full length of the suspended portion of the deck, form runways; beneath these runways are supported the “travellers” required for inspection and painting of the underside of the deck.


The hangers from the arch supporting the deck vary in length from 20 ft to 190 ft at the centre of the bridge. These members are of box section open on two sides and built up of channel-shaped sections of plates and angles laced together transversely. At the top the hanger is provided with eight angles, forming a “V” shaped structure which is attached to the lower chord of the arch.


A SPECIAL TILTING CRADLE used in the construction of the Sydney harbour bridge


















A SPECIAL TILTING CRADLE was used to lift the hangers as one piece into their positions on the main arch. The heavy steel cradle supporting the hanger was hauled up horizontally at first, and then tilted with its load in mid-air so that the hanger was brought into the required vertical position. In the final stages of the operation the hanger and cradle were parted, the former being secured to the arch while the latter was lowered again. The above picture shows the cradle (right) tilted and a long hanger being hoisted into position.



The lower ends of the hangers pass between the webs of the deck cross girders to which they are connected by 14-in diameter steel pins.


Expansion joints are provided the full width of the roadway, and consist of a series of interlocking steel bars attached alternately to either side of the gap - and resemble a pair of large steel combs sliding one within the other. The joints in the footways are covered by steel sliding plates, and the railway track metals are also provided with expansion joints.


The approaches to the bridge are in keeping with the rest of the structure and consist of massive side girders, carrying the deck, supported on granite-faced concrete piers, with foundations carried down to the solid rock. The approach on the north side of the bridge, at Milsons Point, is curved and consists of five spans of 170 ft each. Special calculations were made in designing this approach to allow for the centrifugal stresses imposed by trains rounding the curve. The gradient of the deck rises 1 in 40 at the South end, and 1 in 39 at the North end.


On the South side (Davies Point), the construction is similar to that on the North, except that the approach is straight and the span at the extreme south end is 238 ft instead of 170 ft, on account of an existing road crossing.


The most spectacular masonry work of the structure is to be seen in the immense pylons nearly 300 ft high; these not only form impressive entrances to the central span from the approaches, but they also satisfy the eye in forming an apparent support to the thrust of the arch. Set in the middle of the wonderful natural beauty of Sydney Harbour, these pylons are in keeping with their surroundings. Their architectural treatment lies to the credit of Sir John Burnet and Partners, of London. As structures, the pylons are among the largest yet built in concrete, and involved special problems in design and construction, regarding which the contractors consulted Dr. Oscar Faber, OBE, Minstce.


Solid rock forms the foundation for the pylons, and so thick are the wall bases that pressures are small and the foundations required no special preparations. The area covered by each pylon at ground level is 160 ft by 230 ft. The lower part of each pylon up to the bridge deck level forms a single tower, and above this the structure is continued upwards in the form of two towers, one on either side of the bridge. The twin towers are pierced longitudinally by archways each carrying one footway and one railway track. The two inner tracks and the roadway run in the space between the towers. A roof of reinforced concrete covers each tower, and the outer walls are stiffened by reinforced concrete floors. In the interiors of the towers are steel staircases that give access from ground level to the top.


It is below the front wall of the pylons that excavations were made for the foundations of the arch bearings - enormous pits sunk 30 ft to 40 ft in the solid rock. By reducing the number of joints and thus the number of lifts to be made during construction, a simplified method of building was attained. Cranes capable of handling pieces up to 120 tons were used in the erection of the steelwork. The colossal size of the chord members handled by these cranes will be appreciated when it is remembered that each section comprises a closed box shape with four webs. These vary in depth from 3 ft 4-in to 8 ft 3-in, with flanges 11 ft wide, and the material in the section varies from 6-in to 10-in in thickness.


Workshops in which the construction of the steelwork was carried out were built near the bridge site at Milsons Point. These shops were divided into two departments - “light” and “heavy”. The “light” shop comprised two parallel bays each 500 ft long by 65 ft wide, with a transverse bay, 187 ft long by 70 ft wide, at one end. Equipment included four 25-tons cranes and a crane with two 5-tons grabs in the transverse bay. Above part of this shop was a template loft with a floor 200 ft by 130 ft. The “light” shop was used for the preliminary manufacture of the parts of the main chord before final assembly, and the complete construction of the lighter members and girders.

AN INCOMPLETE PYLON on the Sydney Harbour bridge



















AN INCOMPLETE PYLON. The height of the finished pylons above water level is 285 ft. For building the walls of the pylon structure up to deck level of the bridge - 155 ft above mean sea-level - two 7-tons steam derrick cranes with 110 ft jibs were mounted on four timber towers 105 ft high. The construction of the pylon towers was suspended when the 155 ft level was reached, while the erection of the arch span proceeded; but during this period the placing of a granite facing continued. The “creeper” cranes are shown mounted on the temporary steel ramps.



The “heavy” shop was designed for the construction of the members and the arch trusses. Some of these were of unprecedented dimensions. The shop was 500 ft long and 147 ft wide and was equipped with two 120-tons overhead travelling cranes, each with auxiliary 50-tons hoists. The two cranes were used together when handling complete heavy members of the chords.


The entire plant and tools with which these shops were equipped were supplied by British manufacturers, and the total cost of the workshops, and the site-widening to accommodate them, foundations, wharf buildings, and machine tools, was in the neighbourhood of £300,000.


Included in the plant was a flat-bottomed steel pontoon, 110 ft long by 24 ft beam, with a carrying capacity of 140 tons.


The machines in these workshops were of a remarkable character. That used for planing the edges of steel plates had a capacity up to a length of 66 ft and a thickness of 2¼-in. A Scriven plate straightening machine was used with rolls capable of straightening plates 12 ft wide and 2¼-in thick.


High-Speed Drills


For shearing plates and cutting angles to length special machines were provided capable of “snipping off” pieces of steel up to the maximum thickness of 2¼-in.


Drilling was carried out by a battery of fifty-five Asquith high-speed machines of the fixed, travelling and portable radial types.


A particularly interesting type of drilling machine employed was of the gantry type travelling on a track 13 ft wide on the shop floor. These machines each comprised a massive carriage on wheels, carrying a pair of radial drills capable of drilling holes at any point in an area 12 ft wide by 150 ft long. Nine of these machines were installed, and several of them were placed on the same length of track for simultaneous drilling of the long pieces.


The rivets used for the principal connexions of the structure were of a diameter greater than is generally used even in heavy bridge work. The largest rivets in the bridge are of 1⅜-in diameter and 12 in long. Rivets with a diameter of 1¼-in and a length of grip up to 9-in were commonly used.


All riveting on the bridge site was done by pneumatic hammers. Riveting in the shops was carried out by hydraulic riveters as far as possible, but the closed box form of the members necessitated the use of pneumatic hammers for shop rivets also. The rivet holes were drilled 1/32-in larger than the rivet to allow for expansion of the latter when made red-hot before insertion. After the head of a hot rivet has been formed under pressure, the shank, on cooling, contracts, and so draws the riveted plates tightly together. Before driving, the hot rivets were quenched for a distance of 1½-in from the end.


For finishing to correct length or “ending” the chord sections of the arch a Hulse wall planing machine was employed. This machine, believed to be the largest of its kind ever employed on structural work, was capable of dealing with a surface 12 ft by 10 ft.


A VIOLENT GALE delayed the erection of the first hanger of the Sydney Harbour bridge









A VIOLENT GALE delayed the erection of the first hanger in September, 1930. The hanger, for the support of the main deck, was towed out into the harbour ready for lifting into position, but was caught by a fierce gale and nearly lost. The setting of the hangers presented the engineers with one of the most difficult problems of the bridge.



The planer, despite its size, was capable of an amazing degree of accuracy in the important work on the chord members. It was upon the accuracy of the fitting of chord members, more than any other process, that the final accuracy of the complete structure depended.


After the ending operations on the chord members, the group of members meeting at every panel point was assembled on the floor of the shop, and all rivet holes were reamered to size.


All the principal members of the arch and deck system were fitted with specially designed lifting gear and brackets to facilitate erection. No rope or chain slings were used.


The entire plant and machinery in the shops was electrically driven. Alternating current, 440 volts, 3 phase, 25 cycles, was used for power purposes, and 240 volts for general lighting.


The granite for the piers and pylons was obtained from a quarry provided by the New South Wales Government at Moruya on the coast about 150 miles south of Sydney. The quarry was equipped with the necessary machinery and a wharf. Many of the men were recruited at Aberdeen and sent out to Australia for this work. A small township was built to accommodate the quarrymen and their families. The buildings included a stores, post office, assembly hall and school. Throughout 1925 to 1931 the number of men employed at the quarry was about 240.


The plant and machinery for the quarry was sent out from England, and consisted of four locomotive-cranes for handling the rough masses of granite at the quarry face, a number of pneumatic dressing machines, three 5-tons overhead gantry cranes and a complete installation of oil-driven electric generators and air compressors, locomotives, wagons, and the light railway track on which to run them.


Giant Testing-Machine


For the transport of granite and crushed stone to Sydney, Dorman Long had three single-screw steamers built in New South Wales. Each of these had a carrying capacity of 400 tons and the fleet was operated by the contractors on this service. These vessels on their return journeys brought food supplies and the whole of the drinking water for the quarry employees.


In the steel-framed dressing shops the granite was worked by pneumatic and hand tools to the required shapes The heaviest of the dressed stones weighed 9 tons and the total output of the quarry amounted to 20,000 cubic yards of dressed granite, and 120,000 tons of crushed granite for making concrete.


No risks were taken with so immense a structure as Sydney Harbour Bridge, and an Avery testing machine of 1,250 tons capacity was built to test to destruction large scale models of various parts of the bridge structure.


The first stage in the building of the bridge was the erection of the approach spans and other works on the shores of the harbour. Timber wharves were constructed adjacent to the centre line of the bridge on the Dawes Point and Milsons Point abutments. Plant and materials required for building the approach spans were hauled up specially constructed inclines 1,300 ft long, provided with standard gauge railway track. The inclines were operated by 10-tons electric winches capable of hauling loads up to 70 tons.


CONSTRUCTION WORK IN MID-AIR on the Sydney Harbour bridge










CONSTRUCTION WORK IN MID-AIR. Erecting one of the cross girders for the main span deck. Each cross girder was 160 ft long and weighed up to 110 tons. Cross girders were provided with temporary stagings carrying the 14 in diameter pins, 3 ft in length - one of these can be seen to the left centre of the illustration - for attaching the girders to the hangers. In the picture a hanger with the hole ready for the pin can clearly be seen. The cross girders were finally lifted into correct alinement with the hangers by a crane, and the pins driven home.



Work on the southern approaches was begun first, as the construction site for the north approach was not available for some months later. A 7-tons derrick crane was set up at the extreme southern end of the site, and this was used for placing the concrete forming the southern abutment of the first span.


To enable the construction of the approach span steelwork to be accomplished, two lines of wooden towers, known as “falsework” were built on either side of the bridge centre line. The falsework was constructed of 12 by 12-in beams, and the towers varied in height from 50 ft to 90 ft, according to the contour of the ground. The first section of the falsework was erected by two 5-tons steam loco-cranes built over the southern abutments, and these moved forward on tracks laid over the tops of the towers as the timbering proceeded. When the loco-cranes reached the end of each approach span, they were used for the excavation and building of the piers.


The falsework carried the weight of the approach spans as they were built up panel by panel, and the timbering also supported a gantry track with an 80 ft steel traveller used in erecting the cross-girder frames of the permanent structure.


The riveting of the first span was completed while erection was proceeding with the second. The falsework of the first span was then re-erected for the third span, and the procedure was repeated for all remaining spans. During the building of the approach spans, the steelwork was transported by water from the shops and, after unloading at the wharves, was hauled up the inclines to the required position and lifted on to the falsework.


The construction of foundations for the arch bearings was an undertaking of great magnitude. Excavations for the four bearings were each 90 ft long, 40 ft wide and approximately 40 ft deep. About 50 ft of rock separated the excavations from the water in the harbour, and special walls and coffer dams were constructed to prevent the ingress of water. Every care was taken to ensure that the rock below the excavations was sound. The thrust of the foundations was computed at 13 tons on every square foot of rock. To test the foundation site a number of borings were made with a hollow diamond drill to a depth of 75 ft in the solid rock. On examination of the “cores” taken from the drill it was found that below the excavations the rock was reliable sandstone without cracks or fissures.


The concrete filling, consisting of four parts crushed granite, two parts sand and one part cement, was mixed in a power-driven machine, and placed in the excavations section by section. Each separate section was completed in one operation and allowed to set before the next was placed on or alongside it. The average pressure of the steel bearings on their concrete foundations is 40 tons on every square foot of the base.


The walls of the great pylons are founded on solid rock behind the main bearings, and are of concrete placed between interior timber “shuttering” and the outer granite facing. The facing at the lower levels of the pylons is of very large granite blocks weighing between 5 and 9 tons. The thickness of the pylon walls above a level taken at 27 ft 6-in was generally about 5 ft 6-in, composed of 3 ft 6-in concrete, 1 ft concrete filling, and 1 ft granite facing.


For building the walls of the pylons up to deck level, 155 ft above the base, two 7-tons steam derrick cranes with 110-ft jibs were mounted on four timber towers, 105 ft high.


This picture shows one of the hangers being fixed into position on the Sydney Harbour bridge















51,000 TONS OF STEEL were absorbed in the construction of the bridge, and 38,000 tons of the total went in the building of the arch. All the steel used - with the exception of a small quantity purchased from Australian rolling mills, the main bearings, and some special forgings - was produced from raw materials by Dorman, Long & Co, Ltd, at Middlesbrough, England, and exported to the site. This picture shows one of the hangers being fixed into position.



By the time construction had reached a height of 155 ft the approach span steelwork was completed as far as the pylons, and steelwork for carrying the roadway and railway tracks over the pylon towers was placed in position. Construction of the pylons was suspended at this stage during the erection of the arch span. The placing of the granite facing, however, was continued, and was completed to deck-level by the time work on the pylons could be resumed. To complete the pylons above the 155 ft level the timber towers previously used on the ground were modified and re-erected at this level to carry the two 7-tons derrick cranes. In the upper parts of the pylons the granite facing and concrete walling were built simultaneously.


The triple functions of the great hinge-bearings of the arch have been fully explained earlier in this chapter, namely, to bear the weight of the arch, to hold it against wind pressure, and to allow it to move under the action of heat. The lower chords of each half of the arch - meeting at a point over 800 ft from either shore - were built out from these bearings, and their setting out and erection entailed work of meticulous accuracy.


Two independent base lines were accordingly set out on the North shore at an angle of about 117° to the bridge centre line, each about 1,200 ft long and close to one another, but not parallel. Two independent surveys, using these base lines, were then carried out, and two fixed points were determined, one on either side of the harbour, adjacent to the pylons. A micro-meter-thedolite was used for this work, and the positions of the bearing-pin centres were determined by direct measure-ment from the two fixed points.


Each of the four bearings weighs 300 tons, and is secured by two rows of twelve 4½-in diameter bolts accurately located in a steel template. The bearings were erected first on temporary steel framework above the concrete foundations, and were moved to their correct positions by hydraulic jacks. Finally, after the bearings were set in place the space below them was filled in with high-grade concrete.


The building of the bridge, from either side of the harbour simultaneously, was accomplished by two special “creeper” cranes that were moved forward over the top chords of the arch as work proceeded. Either of these cranes, weighing nearly 600 tons, comprised in itself a number of subsidiary machines for special purposes. The main crane was supported on a rectangular steel framework 148 ft wide, carried on four four-wheeled bogies running on the flange plates of the upper chord.


The main hoist at the end of the 105 ft jib was operated by two 120 hp electric motors capable of lifting a load of 120 tons. The jib was moved up or down by 9-in diameter screws, and the side movement of the main crane was obtained by rack-pinions operated by a 50 hp motor. In addition to the main hoist the jib carried a “jigger” or supplementary hoist capable of moving up, down, or sideways, with a load of 20 tons. The jigger hoist was operated by two 50 hp electric motors.


The main traversing carriage also carried two 2½-tons derrick cranes for dealing with riveting stages, stores, and tools. A further addition was a 5-tons wall crane, mounted on a 50-ft runway on the front girder of the under-carriage. This crane had a 39 ft jib and commanded the whole breadth of the steel structure as far as the arch trusses. Each creeper crane was hauled up the arch chords by cables operated by a 50 hp electric motor, and specially designed safety gear was included in the equipment to guard against failure of the haulage gear. With a 600 tons multiunit crane on the steep slope of the arch a slip of even one inch might have led to disaster.


The creeper cranes were erected by the 25-tons derrick cranes standing on the pylon deck level.


In September, 1928, the erection of the southern arch trusses was begun. The creeper crane was erected on a steel “ramp” on the pylon, ready for transfer to the upper arch chords when completed.


PEDESTRIAN TRAFFIC is catered for on the Sydney Harbour Bridge by two 10 ft wide footways



















PEDESTRIAN TRAFFIC is catered for on the Sydney Harbour Bridge by two 10 ft wide footways, one of which is seen above. The bridge has a roadway in the centre of the bridge 57 ft wide, and the four railway tracks - 4 ft 8½ in gauge - are spaced in pairs on either side of the roadway. One of the track foundations is shown to the left of the footway.



The first portions of the arch to be placed in position were the lowest sections of the lower chord. The end posts, 190 ft long and weighing 70 tons each, were then erected, and supported temporarily by struts from the pylon walls. The end posts were sloped backwards against the wall struts to ensure a gap between the half arches, at the centre, until the time for the final uniting of the arch. Before the first panel could be completed from the end posts it was necessary that these should be secured rigidly against their wall struts to prevent any tendency to “topple” forward into the water.


The end posts were anchored during the building of the arch by 128 steel wire ropes, each 2¾-in diameter and 1,200 ft long. The ropes passed from the top of one end post, , through a U-shaped tunnel in the solid rock behind the pylons, and back to the opposite end post.


The south tunnel was 133 ft long, 25 ft high, and 7 ft wide, with the floor some 100 ft below ground level. The north tunnel was approximately of the same dimensions except tor the length, which, on account of the curvature of the approach, was 170 ft. Both tunnels were lined with concrete, and faced with corrugated steel sheeting shaped to the required curvature. To guide the ropes, special saddles were constructed of reinforced concrete 30 ft long, 10 ft wide, and 30 ft high, pierced by 128 steel tubes, 5-in diameter. Other saddles of steel were placed on the pylons, and attachment to the tops of the end posts was made by special link plates and sockets Each rope, consisting of 217 separate wires, was bound with soft wire 13-in from the end. After insertion in the steel sockets the free ends of the wires were allowed to spread out; 70 of the 217 wires were hooked at the ends. The sockets were then heated and filled with molten white metal. The total tension on the ropes of each completed hall-arch amounted to 14,000 tons.


For the building of the first panel of the arch it was necessary to provide a preliminary anchorage, consisting of eight ropes. After the transfer of the creeper crane from the ramp joining the pylon to the top of the first panel, it was possible to attach the main anchorage ropes. Erection of the panels - upper and lower chords, trusses and diagonals - was then continued.


When the two halves of the arch had been finished, the anchorage ropes were lengthened or “paid out” by special hydraulic and screw gear to enable the lower chords to meet in the centre. Each of the steel ropes was lengthened separately, and the whole process of lowering the half-arches occupied two weeks.


The joints between the lower chords at the top of the arch comprised hinge bearings with 8 in diameter steel pins.


FLAGS WERE FLOWN on the creeper cranes to denote the permanent closing of the lower chords of the arch on the Sydney Harbour bridge















FLAGS WERE FLOWN on the creeper cranes to denote the permanent closing of the lower chords of the arch. The joining of the two completed halves of the great bridge was accomplished by the lengthening of the anchorage ropes. The two creeper cranes weighed each nearly 600 tons, and the main hoists were capable of raising 120 tons at 12½ ft per minute. They were specially designed for this particular construction, as was much of the other equipment.



So that correct alinement could be obtained, the outer ends of the south half-arch were provided with powerful pilot pins 10-in square that engaged with corresponding square holes in the northern halt of the arch. This device could accommodate a divergence in alinement, amounting to 4½-in. So accurately, however, had the bridge been built that the halves met exactly in the transverse direction, and a slight difference vertically was due to expansion, on account of the greater effect of the sun on the northern half-arch.


The arch-halves were permanently in contact on August 19, 1930, and the structure at this stage was supported by three hinges, one at the top and the others at the main bearings.


At this stage all stress at the arch crown was in the lower chords, so that on completion of the upper chords they also had to be subjected to a compression stress. This was necessary to make the completed arch into an absolutely rigid structure resting only on the main bearings at its feet. Accordingly the upper chords were forced apart by hydraulic jacks exerting a pressure of 3,250 tons. Carefully machined steel slabs were then inserted in the gaps between the upper chord members, so completing the arch.


Immediately the arch was finished the creeper cranes began their return journey, building the deck structure as they moved back to the pylons. The cross girders of the deck, 160 ft long and weighing 110 tons each, were floated out under the arch on a pontoon. The girders were lifted off the pontoon by the creeper cranes, and suspended from the lower chord of the arch by hangers. In pictures of the bridge, these hangers, dwarfed by the gigantic arch, appear as mere threads. In fact, however, they are of enormous proportions - the longest measure 190 ft and weigh about 90 tons. Connexion at deck level between Dawes Point and Milsons Point was established on February 17, 1931.


Sydney Harbour bridge was formally opened on March 19, 1932.


You can read more on

“Across Australia by Train”,


“Marvels of Engineering” and


“Travel in Australia”

on this website.



You can read more on

Spanning Sydney Harbour

in Wonders of World Engineering